P.O No :
STAGE | RECEIVED/ COMPLETED | DATE | TIME | REMARKS |
1.CONFORMATION OF APPROVED DRAWING | – | – | – | – |
– | – | – | – | |
2 .DESIGN | – | – | – | – |
– | – | – | – | |
3. STEEL CUTTING | – | – | – | – |
– | – | – | – | |
4. LATHE/ TURNING | RECEIVED | 25-02-25 | 10:31:48 AM | – |
COMPLETED | 25-02-25 | 10:31:59 AM | – | |
5. MILLING | – | – | – | |
– | – | – | ||
6.MODELLING/ PROGRAMMING | – | – | – | – |
– | – | – | – | |
7. CNC MILLING | – | – | – | – |
– | – | – | – | |
8. MANUAL MILLING/M1,M2,M3 | RECEIVED | 25-02-25 | 12:12:31 AM | – |
COMPLETED | 22-02-25 | 10:12:38 AM | – | |
9. HEAT TREATMENT | – | – | – | – |
– | – | – | – | |
10. WIRECUT | – | – | – | – |
COMPLETED | 2025-03-01 | 10:57:47 | – | |
11. EDM | – | – | – | |
– | – | – | ||
12. SIZING/ LOCK FITTING | – | – | – | – |
– | – | – | – | |
13. FINISHING | – | – | – | – |
– | – | – | – | |
14. INSPECTION | – | – | – | – |
– | – | – | – | |
15. DISPATCH | – | – | – | – |
– | – | – | ||
16. Transport Name/LR No. | – | – | – | Track Your LR No. |