P.O No :
STAGE | RECEIVED/ COMPLETED | DATE | TIME | REMARKS |
1.CONFORMATION OF APPROVED DRAWING | – | – | – | – |
– | – | – | – | |
2 .DESIGN | – | – | – | – |
– | – | – | – | |
3. STEEL CUTTING | – | – | – | – |
– | – | – | – | |
4. LATHE/ TURNING | – | – | – | – |
– | – | – | – | |
5.MODELLING/ PROGRAMMING | – | – | – | – |
– | – | – | – | |
6. CNC MILLING | – | – | – | – |
– | – | – | – | |
7. MANUAL MILLING & DRILLING | – | – | – | – |
– | – | – | – | |
8. HEAT TREATMENT | – | – | – | – |
– | – | – | – | |
10. WIRECUT | – | – | – | – |
– | – | – | – | |
11. EDM | RECEIVED | 20/2/2025 | 10:09:54 AM | |
COMPLETED | 20/2/2025 | 10:42:41 | ||
12. SIZING/ LOCK FITTING | RECEIVED | 19/2/2025 | 1:33:41 PM | |
COMPLETED | 19/2/2025 | 1:58:29 PM | ||
13. FINISHING | – | – | – | – |
– | – | – | – | |
14. INSPECTION | – | – | – | – |
– | – | – | – | |
15. DISPATCH | – | – | – | – |
– | – | – | ||
16. Transport Name/LR No. | – | – | – | Track Your LR No. |