P.O No :
STAGE | RECEIVED/ COMPLETED | DATE | TIME | REMARKS |
1.CONFORMATION OF APPROVED DRAWING | – | – | – | – |
– | – | – | – | |
2 .DESIGN | – | – | – | – |
– | – | – | – | |
3. STEEL CUTTING | – | – | – | – |
– | – | – | – | |
4. LATHE/ TURNING | RECEIVED | 25-02-25 | 10:37:31 AM | – |
COMPLETED | 25-02-25 | 10:37:44 AM | – | |
5. MILLING | RECEIVED | 08-03-25 | 2:47:36 PM | |
COMPLETED | 08-03-25 | 5:26:13 PM | ||
6.MODELLING/ PROGRAMMING | RECEIVED | 28-02-25 | 7:17:09 PM | – |
COMPLETED | 28-02-25 | 7:17:23 PM | – | |
7. CNC MILLING | – | – | – | – |
– | – | – | – | |
8. MANUAL MILLING/M1,M2,M3 | RECEIVED | 06-03-25 | 3:29:19 AM | – |
COMPLETED | 06-03-25 | 4:26:32 AM | – | |
9. HEAT TREATMENT | – | – | – | – |
– | 08-03-25 | 8:13:46 PM | – | |
10. WIRECUT | – | – | – | – |
– | – | – | – | |
11. EDM | – | – | – | |
– | – | – | ||
12. SIZING/ LOCK FITTING | – | – | – | – |
– | – | – | – | |
13. LATHE FINISHING | – | – | – | |
– | – | – | ||
14. FINISHING | – | – | – | – |
– | – | – | – | |
15. INSPECTION | – | – | – | – |
– | – | – | – | |
16. DISPATCH | – | – | – | – |
– | – | – | ||