P.O No :
STAGE | RECEIVED/ COMPLETED | DATE | TIME | REMARKS |
1.CONFORMATION OF APPROVED DRAWING | – | – | – | – |
– | – | – | – | |
2 .DESIGN | – | – | – | – |
– | – | – | – | |
3. STEEL CUTTING | – | – | – | – |
– | – | – | – | |
4. LATHE/ TURNING | RECEIVED | 25-02-25 | 10:37:08 | – |
COMPLETED | 25-02-25 | 10:37:19 | – | |
5. MILLING | RECEIVED | 08-03-25 | 17:27:22 | |
– | – | – | ||
6.MODELLING/ PROGRAMMING | RECEIVED | 28-02-25 | 18:52:01 | – |
COMPLETED | 28-02-25 | 19:16:51 | – | |
7. CNC MILLING | – | – | – | – |
– | – | – | – | |
8. MANUAL MILLING/M1,M2,M3 | RECEIVED | 06-03-25 | 1:04:27 | – |
COMPLETED | 06-03-25 | 3:29:08 | – | |
9. HEAT TREATMENT | RECEIVED | 08-03-25 | 20:13:56 | – |
– | – | – | – | |
10. WIRECUT | – | – | – | – |
– | – | – | – | |
11. EDM | – | – | – | |
– | – | – | ||
12. SIZING/ LOCK FITTING | – | – | – | – |
– | – | – | – | |
13. LATHE FINISHING | – | – | – | |
– | – | – | ||
14. FINISHING | – | – | – | – |
– | – | – | – | |
15. INSPECTION | – | – | – | – |
– | – | – | – | |
16. DISPATCH | – | – | – | – |
– | – | – | ||
17. Transport Name/LR No. | – | – | – | Track Your LR No. |