GTQ00011926

P.O No :

STAGERECEIVED/ COMPLETEDDATETIMEREMARKS
1.CONFORMATION OF APPROVED DRAWING
2 .DESIGN
3. STEEL CUTTING
4. LATHE/ TURNINGRECEIVED21-02-251:01:42 PM
COMPLETED21-02-251:02:09 PM
5. MILLINGRECEIVED25-02-259:49:06 AM
COMPLETED25-02-2511:17:51 AM
6.MODELLING/
PROGRAMMING
7. CNC MILLING
8. MANUAL MILLING/M1,M2,M3RECEIVED25-02-2512:12:31 AM
COMPLETED22-02-2510:12:38 AM
9. HEAT TREATMENT
COMPLETED25-02-258:18:59 PM
10. WIRECUTRECEIVED25-02-2512:18:38 PM
COMPLETED25-02-252:47:31 PM
11. EDM
COMPLETED20-02-2510:09:27 AM
12. SIZING/ LOCK FITTINGRECEIVED01-03-259:38:35 AM
13. FINISHING
14. INSPECTION
15. DISPATCH
16. Transport Name/LR No.Track Your LR No.

bp0yknq7