P.O No :
STAGE | RECEIVED/ COMPLETED | DATE | TIME | REMARKS |
1.CONFORMATION OF APPROVED DRAWING | – | – | – | – |
– | – | – | – | |
2 .DESIGN | – | – | – | – |
– | – | – | – | |
3. STEEL CUTTING | – | – | – | – |
– | – | – | – | |
4. LATHE/ TURNING | RECEIVED | 21-02-25 | 7:29:49 PM | – |
COMPLETED | 21-02-25 | 7:30:03 PM | – | |
5.MODELLING/ PROGRAMMING | – | – | – | – |
– | – | – | – | |
6. CNC MILLING | – | – | – | – |
– | – | – | – | |
7. MANUAL MILLING/M1,M2,M3 | – | – | – | – |
– | – | – | – | |
8. HEAT TREATMENT | – | – | – | – |
– | – | – | – | |
10. WIRECUT | RECEIVED | 22-02-25 | 9:45:43 PM | – |
COMPLETED | 23-02-25 | 12:12:23 AM | – | |
11. EDM | – | – | – | |
– | – | – | ||
12. SIZING/ LOCK FITTING | RECEIVED | 25-02-25 | 11:05:10 AM | |
COMPLETED | 25-02-25 | 11:38:10 AM | ||
13. FINISHING | – | – | – | – |
– | – | – | – | |
14. INSPECTION | – | – | – | – |
– | – | – | – | |
15. DISPATCH | – | – | – | – |
– | – | – | ||
16. Transport Name/LR No. | – | – | – | Track Your LR No. |